Limits: 700' west of US12 to Holly Circle in the village of Lake Zurich

Description: Widening and resurfacing to provide left turn lanes on Miller Rd. Sidewalks will also be added.

Construction

Current Information

12/19/2023 - Utility relocations are still in progress. We anticipate relocations to be complete in the spring of 2024. The intersection improvement work will begin following completion of utility relocations. should begin in Spring of 2024