Hart Rd Bridge

Limits: Between Lake Cook Rd and US14 (Northwest Hwy) in the village of Barrington

Description: Replace aging triple culverts with a bridge, adding bike path on the east side of the bridge which will be extended by the Village of Barrington. Includes resurfacing of Hart Rd from Lake Cook Rd to south of US14. A 155-day closure and detour will be necessary for bridge construction.

Construction

Current Information


8/12/2022 - The bridge deck has been framed and rebar installation is in progress. Also, crews are currently grading ditches and embankment. 

For week of 8/15, crews will finish rebar installation and plan to pour the concrete deck on Wednesday. The contractor also plans to finish framing both retaining walls on the east side of Hart Rd and pour the concrete walls later in the week.

Traffic Impacts: Hart Rd is now closed. Please follow detour. Watch for trucks coming in and out of the jobsite.