Hart Rd Bridge

Limits: Between Lake Cook Rd and US14 (Northwest Hwy) in the village of Barrington

Description: Replace aging triple culverts with a bridge, adding bike path on the east side of the bridge which will be extended by the Village of Barrington. Includes resurfacing of Hart Rd from Lake Cook Rd to south of US14. A 155-day closure and detour will be necessary for bridge construction.

Construction

Current Information


9/30/2022 - Wetland plantings along the creek and pavement removal on the north side of the bridge are completed. Crews are currently building the new road base at the north side and prepping the shoulders on the west side of Hart Rd. 

For week of 10/3, crews will complete the road base, prep shoulders, and shape ditches. The contractor plans to start paving binder at the north and south side of the bridge towards the end of the week. They also plan on paving binder for the HMA shoulders. Concrete staining to begin next week.  

Traffic Impacts: Hart Rd is now closed. Please follow detour. Watch for trucks coming in and out of the jobsite.