IL Route 83 Force Main Realignment

Project Location: East side of Illinois Route 83, approximately 300 feet north of the intersection of Illinois Route 83 and Heather Knoll Court in the Long Grove area.  

Project Description:  Realignment of sanitary sewer force main to modernize piping for future maintenance. The contractor will need to work in the right of way of Illinois Route 83, which will require off peak travel times temporary one lane closures. Please allow for extra travel time and use caution when traveling through the work zone.


Project Images

  1. 1
  2. 2
  3. 3

Current Phase/Anticipated Schedule:

Construction began last fall and the project timeline was altered due to an unforeseen underground utility conflict. As of late May, utility relocation work is complete. The force main realignment work is anticipated to begin in late July 2022. 

  1. Project Contact
  2. Project Documents

Tom Miles, P.E.  
Principal Civil Engineer 
847-377-7500 
[email protected]