Sunset Ave Signals
Limits: From McAree Rd to Sheridan Rd in Waukegan
Description: Replacement of signals at Sunset/McAree, Sunset/Yeoman, and Golf/Jackson, plus signal interconnect work extending through Sheridan Rd. Temporary signals will be in place until new signals are installed.
Current Information
6/8/2022 - This project is mostly complete. The contractor has a few adjustments to make to the traffic signals but no future impacts to traffic are expected.
Project Images
-
Finished signal Sunset_McAree (June 2022)
-
Finished signal Golf Yeoman (June 2022)
-
Fisnished signal Golf Jackson (June 2022)
-
Permanent Signal Golf and Jackson (Mar2022)
-
Finishing sidewalk (Oct 2021)
-
Pouring curb on Sunset (Sept 2021)
-
Temporary signal installed at Sunset and McAree (June 2021)
-
GolfandYeoman preconstruction (Apr2020)
-
SunsetandMcAree preconstruction (Apr2020)
-
GolfandJackson preconstruction (Apr2020)
Joe Munno, Resident Engineer
Lake County Division of Transportation
600 W Winchester Rd
Libertyville, IL 60048-1381
[email protected]
847-377-7400
3/8/2022 - The permanent traffic signals have been installed. We are currently waiting on ComEd to hook up the new signals to power and then a turn on will be scheduled. Once the new signals are turned on, the temporary signals will be removed.
10/18/2021 - The contractor is continuing to pour handholes and foundations for the new traffic signals. As they are finishing the handholes and foundations, they are replacing the sidewalk that was removed.
9/22/2021 - The contractor has finished installing the underground conduit and has poured the curb at all three intersections. Currently pouring handholes and foundations for the new traffic signals.
8/9/2021 - The contractor is continuing to install conduit along Sunset Ave and at Sunset/McAree, Golf/Yeoman, and Golf/Jackson.
6/30/2021 - Temporary traffic signals have been installed at Sunset & McAree, Golf & Yeoman, and Golf & Jackson. In the coming weeks, the contractor will be working on removing the existing traffic signal foundations and installing conduit along Sunset Ave/Golf Rd.
3/29/2021 - Awaiting Com Ed pole & aerial cable relocations at Yeoman intersection in April. Then project can begin with temporary signals at all three intersections in May.
3/2/2021 - Replacement of signals at Sunset/McAree, Sunset/Yeoman, and Golf/Jackson, plus signal interconnect work extending through Sheridan Rd. Temporary signals will be in place until new signals are installed.