Limits: From IL60 to north of IL120 near Round Lake

Description: Asphalt resurfacing and install bike-friendly shoulders. The work will include storm sewer (No Road Crossings) and driveway culvert pipe replacement. Work will also include Curb & Gutter replacement. Both sections of the roadway will be affected by this work.

Construction

Current Information


9/15/2020 - The contractor has completed the remaining asphalt shoulder work. A continuous 4 Foot Bike-Friendly shoulder is now available from IL 60 to north of IL 134. Only final landscaping along the added bike-friendly shoulder remains. The project is expected to be completed this week.