Fairfield Rd Resurfacing
Limits: From Nippersink Rd to IL132 in Round Lake, Round Lake Beach, Round Lake Heights, and Lake Villa.
Description: Asphalt resurfacing and installation of bike friendly shoulders
Current Information
9/16/2020:
Fairfield Rd (Monaville Rd to IL32): project is now complete.
Fairfield Rd (Nippersink Rd to IL134): This section was paved and striped in fall 2019, minor work items remain. All work is expected to be complete this week.
Project Images
-
Preconstruction (March 2019) Fairfield pavement patches over multiple years
-
Preconstruction (March 2019) Wilson at IL60
-
Preconstruction (March 2019) Fairfield pavement condition at 134
Paul Guardi, Resident Engineer
847-377-7483
Lake County Division of Transportation
600 W Winchester Rd
Libertyville, IL 60048-1381
dot@lakecountyil.gov
847-377-7400
11/19/2019 -
Fairfield Rd (Nippersink Rd to IL RTE 134) – The first layer of asphalt has been completed. A material that helps preserve the paving joints is planned to be place tomorrow (11/20/19). The paving of the final surface will follow as weather allows.
-Fairfield Rd (Monaville Rd to IL RTE 132) – Final Surface has been paved. Crews are currently working on paving driveways. Striping and Aggregate shoulder work will follow as weather allows
11/8/2019 -
-Fairfield Rd (Nippersink Rd to IL RTE 134) – Fairfield Rd between IL RTE 134 and IL RTE 120 is now open to all traffic. The roadway was opened just after 4:00 PM today.
-Fairfield Rd (Monaville Rd to IL RTE 132) – The first layer of asphalt was paved prior to the snowfall. The next step will be to widen the shoulders of the road and pave them. The final surface will follow. Minor landscaping restoration is also needed.
11/5/2019 -
-Fairfield Rd (Nippersink Rd to IL RTE 134) – Surface Removal is complete, patching was scheduled but we then received the snow. Patching is not rescheduled for Wednesday 11/6/19. Priming (Oil) of the road will follow. Minor landscaping restoration is also needed.
10/21/2019 -
-Fairfield Rd (Nippersink Rd to IL RTE 134) – Surface removal is set to begin 10/24/2019 (Thursday). Minor landscape work will also occur at some point. The roadway will be paved this year, although it may not be the final surface. The roadway will be made plowable before a winter shutdown. Driveways will be made plowable if not replaced this year.
-Fairfield Rd (Monaville Rd to IL RTE 132) – Begin removing existing surface 10/22/2019 (Tuesday). Minor landscape restoration work at some point. The roadway will be paved this year, although it may not be the final surface. The roadway will be made plowable before a winter shutdown. Driveways will be made plowable if not replaced this year.
10/15/2019 -
-Fairfield Rd (Nippersink Rd to IL RTE 134) – Large planned patch is complete. Surface removal is likely to begin late week of 10/21/19, due to unplanned storm sewer work that needs to happen first. Minor landscape work will also occur at some point.
-Fairfield Rd (Monaville Rd to IL RTE 132) – Begin removing existing surface (Week of 10/21/19) and minor landscape restoration work. Removal has been delayed due to prep work that needs to be complete before surface removal happens.\
10/4/2019 -
Fairfield Rd (Nippersink Rd to IL RTE 134) – Begin a large planned patch in the SB lane near the frisbee golf course with possible lane shifts Saturday 10/5/19 (This will take a few days to complete). This will be followed by the removal of the existing surface of the entire road.
Fairfield Rd (Monaville Rd to IL RTE 132) – Begin removing existing surface (late week of 10/7/19) and minor landscape restoration work.
9/26/2019 -
Fairfield Rd (Nippersink Rd to IL134) – Begin removing existing surface (week of 9/30/19), planned patching of the southbound lane at Disc Golf Course, storm sewer repairs/replacements and minor landscape restoration work.
Fairfield Rd (Monaville Rd to IL132) – Begin removing existing surface (week of 9/30/19) and minor landscape restoration work.
9/17/2019 -
Fairfield Rd (Nippersink Rd to IL134) – Backfilling of newly poured curb.
Fairfield Rd (Monaville Rd to IL132) – Curb inlet repair, pouring replacement curb, ditching work at driveway culverts that were replaced
9/4/2019 - The Fairfield Rd Resurfacing project will be starting next week (9/9/19). Sections of this project include:
Fairfield Rd (Nippersink Rd to IL RTE 134)
Fairfield Rd (Monaville Rd to IL RTE 132)
The work that will occur next week will include storm sewer (No Road Crossings) and driveway culvert pipe replacement. Work will also include Curb & Gutter replacement. Both sections of roadway will be affected by this work. This work will likely last a few weeks. Will be starting next week (9/9/19).