St. Mary's Rd/Everett Rd 3R

Limits: St. Mary's Rd from IL Rte 60 to Everett Rd in Mettawa and Everett Rd from St. Mary's Rd to east of I-94 bridge in Lincolnshire, Mettawa and Lake Forest.

Description: This project consists of asphalt resurfacing, installation of bike friendly shoulders, ditch grading and drainage improvements, and forest preserve bike path work.

Progress Bar (Construction)

Current Information

 


7/29/2019 - This week, the contractor will be wrapping up all concrete work items and ditch grading. In the first few weeks of August, milling of the existing pavement will begin, beginning with the Riverwoods & Everett roundabout. This work will take place during night time hours to reduce traffic delays. This pavement milling is scheduled for the end of the week.

Please use caution while driving through the work zone as daily lane closures will be utilized. Watch for flaggers, workers and equipment. 




Project Images

  1. Documents
  2. Contact Information
  3. Previous Updates