Description: Plans are being prepared for a new traffic signal to be installed at the intersection of Wilson Road and Nippersink Road.

Construction

Current Information

2/20/18 - Tree removal is complete. Nicor has installed their new gas mains and is currently coordinating the final connections to complete the majority of their work. When the final connections are made they will be onsite for an additional few weeks removing the old gas lines. They will continue to use lane closures as necessary. AT&T is currently working on installing new cable and once active the old cable and short poles will be removed. The new cables are expected to be installed by early March. The general contractor (Berger) has minor work this week off road in the newly cleared areas. They will be installing erosion control east of Wilson Road.