Hart Rd Bridge
Limits: Between Lake Cook Rd and US14 (Northwest Hwy) in the village of Barrington
Description: Replace aging triple culverts with a bridge, adding bike path on the east side of the bridge which will be extended by the Village of Barrington. Includes resurfacing of Hart Rd from Lake Cook Rd to south of US14. A 155-day closure and detour will be necessary for bridge construction.
Current Information
8/12/2022 - The bridge deck has been framed and rebar installation is in progress. Also, crews are currently grading ditches and embankment.
For week of 8/15, crews will finish rebar installation and plan to pour the concrete deck on Wednesday. The contractor also plans to finish framing both retaining walls on the east side of Hart Rd and pour the concrete walls later in the week.
Project Images
-
Finished deck framing (August 2022)
-
Deck rebar installed looking NW (August 2022)
-
Placing the first beam (August 2022)
-
Setting beams in place (August 2022)
-
Framing the bridge deck (August 2022)
-
Framing the bridge deck (August 2022)
-
Installing storm sewer north of Barrington HS (July 2022)
-
Completed river rock on west side (July 2022)
-
Installing rebar north retaining wall (July 2022)
-
Placing river rock at NW creek (July 2022)
-
Placing temporary soil stabilization (July 2022)
-
Pouring concrete in piles (July 2022)
-
Driving H-piles south wall (July 2022)
-
Installing storm sewer (July 2022)
-
Installing river rock (July 2022)
-
Removing temporary sheet piling (July 2022)
-
Pouring north and excavating south abutment (July 2022)
-
Driving piles for south abutment (July 2022)
-
Piling-weld splice ring south abutment (July 2022)
-
Pile driving (July 2022)
-
Pouring concrete in shell piles (July 2022)
-
Torch cutting old culvert (June 2022)
-
Removing bottom half culvert (June 2022)
-
Removing old culvert (June 2022)
-
Rip rap installation near north abutment (June 2022)
-
Test pile (June 2022)
-
Temporary sheeting piling installation (June 2022)
-
Grinding and pavement removal (June 2022)
-
Grinding and pavement removal (June 2022)
-
Silt fence installation (June 2022)
-
Hart Rd closure (June2022)
-
Guardrail removal e.side Hart Rd (June2022)
-
Guardrail removal w.side Hart Rd (June2022)
-
Hart Rd Bridge
Jeff Dayson, Resident Engineer
Lake County Division of Transportation
600 W Winchester Rd
Libertyville, IL 60048-1381
[email protected]
847-377-7400
8/5/2022 - Bridge beams have been set and concrete deck framing currently in progress. For week of 8/8, crews will begin installing the steel reinforcement bars in the deck and start excavating/grading ditches.
7/29/2022 - Storm sewer work south of the creek in progress. Crews plan to set the bridge beams on Monday (8/1) and begin framing the concrete bridge deck later in the week. They will also continue storm sewer installation week of 8/1.
7/22/2022 - River rock installation along the creek and retaining wall construction is in progress. For week of 7/25, crews will continue constructing the north and south retaining wall and work on storm sewer installation just north of Barrington High School intersection. Also, contractor might set bridge beams towards the end of the week.
7/15/2022 - North bridge abutment and wingwall has been completed. The south abutment and wingwall have been poured. Work on south retaining wall and storm sewer is in progress. For week of 7/18, crews will continue building the south retaining wall, storm sewer and channel excavation/grading. Contractor will also begin driving H-piles and construction of the north retaining wall.
7/8/2022 - North bridge abutment and wingwall construction is in progress. Also, crews are currently working on driving piles for the south abutment. For the week of 7/11, the contractor will continue driving piles for the south abutment and begin channel excavation/river rock installation and storm sewer work.
7/1/2022 - The last culvert pipe has been removed and pile driving for the north bridge abutment has been completed. Rip rap installation on the south side of the bridge in progress. For week of 7/5, pile driving crew will relocate to the south side and begin driving piles for the south abutment. Also, the contractor will begin frame work for the north abutment.
6/24/2022 - The existing middle and north pipe culvert has been removed. Rip rap installation in progress for north abutment. For week of 6/27, crews plan on driving piles for the north abutment, beginning work for the north retaining wall on east side of Hart Rd, and removing the last culvert pipe (south piece).
6/17/2022 - Existing pipe culvert removal in progress. For week of 6/20, crews will continue removing the old pipe culvert and begin bridge excavation work.
6/10/2022 - Tree removal has been completed. Pavement removal and silt fence installation in progress. For the week of 6/13, crews will be doing some miscellaneous prep and excavation work for pile installation. Contractor plans on driving test piles for the bridge around midweek.
6/3/2022 - Hart Road is now closed and construction work has started. Crews have started working on guardrail removal. Week of 6/6 crews will continue guardrail removal, begin tree removals, install silt fence and other erosion control items, fence and pavement removal.