Wilson Rd: at Nippersink Rd

Limits: .25-mile in each direction from the intersection of Wilson Rd and Nippersink Rd in Round Lake and Grant township

Description: This project consists of pavement reconstruction with a new signalized intersection, retaining wall on NW and SE corners, and shared-use path along south side of Nippersink Rd and east side of Wilson Rd north of Nippersink Rd, pavement markings and related work.

SIGN UP to receive email updates for this project

Progress Bar (Construction)

Current Information


9/11/18 - The contractor has completed the majority of the storm sewer work for this stage of the project. Crews have excavated and began building the base for the pavement. The contractor expects to finish placing the roadway base and begin prepping for the new concrete curb this week. Following curb installation, paving of the new roadway will begin. Crews will continue to form and pour the south retaining wall. Once completed they expect to begin on the north wall. Final landscaping will also begin as parts of the new roadway are installed.

Coming weeks: Permanent and additional temporary pavement will be paved on Wilson Road and eventually traffic shifted to the east on Wilson Road. Once the south wall work is complete, crews will begin working to install the concrete facing on the north wall. Crews will continue to install storm sewer as traffic is shifted to the new pavement.

Traffic impacts: Watch for workers and flaggers as daily lane closures are being utilized for concrete and other excavation work. Watch for trucks coming in and out of the jobsite. Expect delays. Please note that Big Hollow school district classes have resumed.



Project Images

  1. Documents
  2. Contact Information
  3. Previous Updates
No documents available.