Greenleaf St - N of IL 120 to Washington St

Limits: From the north ramps of IL120 to the south edge of Washington St in the Village of Gurnee and the Cities of Waukegan and Park City.

Description: The project consists of asphalt resurfacing and the installation of bike friendly shoulders. Staged construction will also be necessary to replace a large culvert near Cornell Av. Concrete median near IL120 will be replaced with a planted median in cooperation with Park City. 

Progress Bar (Construction)

Current Information


8/29/17 - This project kicked off at the end of July. The culvert replacement near IL 120 is complete. Concrete curb work started this week, and milling and resurfacing work will follow. Please watch for workers and equipment and drive safely. 

Project Images

  1. Documents
  2. Contact Information
  3. Previous Updates
No documents available.