Darrell Rd - IL 176 to South of Burnett Rd

Limits: From the north side of IL176 to 900’ south of Burnett Rd in the Village of Island Lake

Description: The project consists of asphalt resurfacing and the installation of bike friendly shoulders.

Progress Bar (Construction)

Current Information


10/2/17 - The contractor has completed paving the first layer of asphalt on Darrell Road. Shoulder widening and paving for the new Bike-Friendly shoulders is also complete. Crews recently completed prepping driveways and electrical crews have begun replacing detector loops. Final surface paving will begin next week.

Project Images

  1. Documents
  2. Contact Information
  3. Previous Updates
No documents available.