Hawley St - From East of Seymour Ave to Midlothian Rd

Limits: From Midlothian Rd to just east of Seymour Av in the Village of Mundelein.

Description: The existing road was reconstructed to 3 lanes of asphalt pavement; 1 lane in each direction and a center turn lane, with a new traffic signal installed at California Av. The watermain, sanitary and storm sewer systems were replaced. A concrete/asphalt bike path was constructed as well as concrete sidewalks and curb.

Progress Bar (Complete)

Current Information


This project is complete.

Project Images

  1. Documents
  2. Contact Information

Project Documents